Case Study · No. 010 · Pyrogel® XTE
Pyrogel® XTE
Petrochemical
Brazil

Petrochemical facility in São Paulo, Brazil.

Cost savings by addressing the root cause of process instability.

40 km of steam piping ran through a flood-prone service trench. Mineral wool and cal-sil were waterlogged year-round, and CUI was advancing fast. Pyrogel® XTE kept the system dry and recovered $1.3M per year.

$1.3M/yr
saved on steam-line efficiency improvement

40 km steam-line piping · flood-prone trench

40 km steam-line piping · flood-prone trench

Product
Pyrogel® XTE
Industry
Petrochemical
Application
40 km steam-line · service trench
Location
São Paulo, Brazil

01 · The Challenge

Tropical rain, a flooded service trench, and 715 °F steam.

The piping ran through a service trench that flooded routinely, with UV-degraded jacketing letting moisture into already-failing fibrous insulation.

  • Flooded service trench. Geography made periodic flooding inevitable; jacketing failed under UV and rain.
  • Degraded mineral wool and cal-sil. Wet, falling off, and locally absent — accelerating CUI.
  • Steam quality collapsed during rain. Downstream units forced into shutdown when the trench flooded.
  • CUI on high-pressure steam line. A catastrophic risk on a 715 °F service.

02 · The Solution

Pyrogel® XTE kept the steam line dry and stable.

Pyrogel® XTE’s hydrophobicity removed the moisture path; process stability returned and the rental-boiler workaround was no longer needed.

  • Kept steam line dry and operating efficiently. Hydrophobic blanket survives the trench environment.
  • Process stability through wet weather. Downstream units no longer forced offline during rain events.
  • Rental boilers eliminated. Capacity workaround was no longer required to maintain steam supply.
  • Payback under 8 months. ROI on the material investment was rapid.

03 · The Outcome

$1.3M per year in energy and stability savings.

Pyrogel® XTE’s combination of dry-in-service performance and CUI resistance delivered $1.3M per year on this site’s steam network — and removed the operational cost and reliability risk of running rental boilers as a weather workaround.

$1.3M/yr
Energy savings
Recovered from the steam-line efficiency improvement.
40km
Pipe scope
Of steam line re-insulated across the service trench.
<8mo
Payback
On the material investment.

Insulation under water? Process down when it rains?

Aspen’s hydrophobic blankets are engineered for trench and tropical service.