Case Study · No. 002 · Pyrogel® XTE
Pyrogel® XTE
Petrochemical
Taiwan

Petrochemical complex on the Taiwanese coast.

Downtime rescue with long-term, superior asset protection.

A 2020 inspection at a coastal petrochemical complex revealed severe CUI — with tower sections having lost 40% of their thickness. Pyrogel® XTE compressed the remediation window and recovered lost production revenue.

>$8M
in recovered downtime revenue

RFCC tower · high-temperature CUI mitigation

RFCC tower · high-temperature CUI mitigation

Product
Pyrogel® XTE
Industry
Petrochemical
Application
RFCC tower · high-temperature service
Location
Taiwan

01 · The Challenge

Severe CUI threatened a major unplanned downtime event.

A scheduled inspection revealed corrosion that had been progressing for years under intact-looking insulation.

  • Severe CUI discovered. 40%+ wall-thickness loss on tower sections, identified during a 2020 inspection.
  • Reduced selectivity, then metal loss. Process performance had been off-baseline, prompting the inspection.
  • High risk of major downtime. Without an accelerated remediation plan, the unit faced weeks of unscheduled shutdown.

02 · The Solution

Pyrogel® XTE mitigated future CUI and recovered the schedule.

Pyrogel® XTE’s faster application compressed the metal-remediation window and accelerated restart.

  • Mitigated future CUI events. Hydrophobic blanket eliminates the moisture pathway that drove the original failure.
  • Recovered metal-remediation time. Faster insulation application freed schedule used for additional metal work.
  • Completion 20 days ahead. Integrated remediation + re-insulation closed out faster than the original plan.
  • Captured lost downtime revenue. Earlier restart converted directly into revenue that would otherwise have been lost.

03 · The Outcome

8× return on investment from accelerated restart.

The operator captured an 8× return on investment — recovered production days dwarfed the material premium over traditional insulation. The site recorded the project as a downtime-rescue case and added Pyrogel® XTE to the spec for future CUI work.

Return on investment
Recovered downtime revenue vs material premium.
>$8M
Revenue captured
From the earlier-than-planned restart.
20days
Ahead of schedule
Remediation + re-insulation completed early.

Discovered CUI on a critical tower?

Talk to an Aspen engineer about a Pyrogel® XTE remediation plan that fits your turnaround window.