Case Study · No. 016 · Pyrogel® HPS
Pyrogel® HPS
Refining
USA

Delayed coker at a refinery on the Texas Gulf Coast.

Improved yield driven by superior thermal performance.

Four DCU coke drums needed re-insulation — but without taking the unit offline. Pyrogel® HPS was installed between cycles, contributing to harder coke, lower volatile-combustible matter, and meaningful per-month margin lift.

$30–50k/mo
in incremental margin from lower volatile-combustible matter

DCU coke drums · live re-insulation

DCU coke drums · live re-insulation

Product
Pyrogel® HPS
Industry
Refining
Application
Delayed coker · 4 DCU coke drums (live re-insulation)
Location
Texas, USA

01 · The Challenge

Re-insulate four coke drums without taking the unit down.

Any conventional re-insulation campaign would have required a shutdown — costly on a delayed coker. The operator wanted zero-downtime work.

  • Four DCU coke drums to re-insulate. Major scope at the heart of the unit.
  • Zero-downtime requirement. Operator unwilling to take the coker offline for the work.
  • Inspection windows tight. Circumferential welds inspected routinely — needed removable covers.

02 · The Solution

Pyrogel® HPS between cycles, with site-fabricated inspection blanks.

Work was scheduled between cycles; the on-site contractor fabricated their own HPS-filled inspection blanks for routine weld access.

  • Installed between cycles · zero downtime. No production interruption for the re-insulation campaign.
  • Optimized operating temperature. Pyrogel® HPS held temperature reliably across the drum cycle.
  • Harder coke; lower VCM. Both indications of improved liquid yield from the drum.
  • Site-fabricated HPS inspection blanks. Maintained routine weld-inspection workflow.

03 · The Outcome

Per-month margin lift from improved drum yield.

Post-install audit showed lower surface temperatures, harder coke that was difficult to cut, and a measurable VCM reduction — worth approximately $30–50k per month in incremental margin on the unit, with further upside available as the operator optimizes furnace temperatures.

$30–50k/mo
Margin uplift
From VCM reduction post-install.
4
Coke drums re-insulated
All four, between cycles, zero downtime.
0
Production interruption
Unit ran throughout the re-insulation campaign.

Need to re-insulate coke drums without taking the unit down?

Pyrogel® HPS installs between cycles — Aspen can scope a zero-downtime re-insulation plan.