Catalytic reformer at a refining/chemical complex in Texas, USA.

Increased revenue by returning to service in record time.

An unplanned shutdown left only three days to re-insulate a catalytic reformer — and the incumbent perlite required six. Pyrogel® XTE went in inside the three-day window, returning the unit to service ahead of schedule.

3days
to re-insulate a 45,900 bpd catalytic reformer

Catalytic reformer · live-window re-insulation

Catalytic reformer · live-window re-insulation

Product
Pyrogel® XTE
Industry
Refining
Application
Catalytic reformer · unplanned shutdown re-insulation
Location
Texas, USA

01 · The Challenge

3 days of window, 6 days of perlite.

The site had already purchased perlite to re-insulate the unit, but the unplanned shutdown collapsed the available window from six days to three.

  • Unplanned shutdown mid-TAR. Window dropped from planned to emergency.
  • Perlite already purchased. Material was on site, but its install time exceeded the available days.
  • $250k revenue lost per operational day. Every additional shutdown day had a direct, large-dollar cost.

02 · The Solution

Switch to Pyrogel® XTE inside the three-day window.

An on-site engineer proposed Pyrogel® XTE; the team converged within the morning, took delivery the same afternoon, and installed inside three days.

  • Pyrogel® XTE re-insulated in record time. Installed in 3 days versus 6 with the original perlite spec.
  • Benefit of time exceeded sunk material cost. Operator agreed to absorb the perlite write-off.
  • ROI under 2.1 days. Revenue recovered from earlier restart paid for the material almost immediately.
  • Reusable for future inspections. Material can be removed for inspection and reinstalled.
  • ~150 rolls of Pyrogel® XTE. Delivered same-day from distribution.

03 · The Outcome

50% faster turnaround and a $750K revenue gain.

The substitution to Pyrogel® XTE compressed the insulation phase by half and returned the unit to service in time to capture roughly $750k in revenue that would have otherwise been lost. The operator added Pyrogel® XTE to plans for the upcoming sitewide rejuvenation program.

50%
Faster turnaround
3-day install vs 6-day perlite spec.
~$750k
Revenue gained
From the earlier-than-planned restart.
<2.1days
ROI
Investment recovered almost immediately.