Case Study · No. 013 · Pyrogel® XTE · Pyrogel® XTF
Pyrogel® XTE
Pyrogel® XTF
Refining
USA

Amine still at a refinery in Texas, USA.

Schedule assurance with a lightweight insulation solution.

A 78.2-ft × 126-in amine still had a hard weight budget on its foundation pad. Pyrogel® XTE and XTF replaced calcium silicate and Pyrocrete®, cutting 6,000 lb of installed weight with equivalent thermal and PFP performance — and completing 10 days ahead of schedule.

6,000lb
of installed weight removed from the amine still

Amine still · 78.2-ft × 126-in vessel

Amine still · 78.2-ft × 126-in vessel

Product
Pyrogel® XTE · Pyrogel® XTF
Industry
Refining
Application
Amine still · 78.2 ft × 126 in
Location
Texas, USA

01 · The Challenge

A foundation pad with a hard weight budget.

The pad would have needed civil upgrade work to carry the original cal-sil + Pyrocrete® system.

  • Foundation-pad weight limit. No headroom to add traditional insulation + PFP weight.
  • Required reduction of installed weight. 78.2-ft × 126-in still — a major vessel.
  • Thermal performance and PFP could not be compromised. Substitution had to be functionally equivalent.

02 · The Solution

Pyrogel® XTE + XTF replaced cal-sil + Pyrocrete®.

Combined into a single lighter package: 30 mm XTE on the vessel, 60 mm XTF on the skirt and head.

  • 30 mm XTE on the vessel. Equivalent thermal performance to the cal-sil spec.
  • 60 mm XTF on the skirt and head. Equivalent PFP performance to the Pyrocrete® spec.
  • Foundation-pad upgrade avoided. Civil works eliminated from the scope.
  • 4 insulators, 8-hour shifts. Crew completed installation pre-TAR with a small team.
  • 10 days ahead of schedule. Full insulation completed early.

03 · The Outcome

Civil work avoided. Schedule beaten by 10 days.

The lighter Pyrogel® package eliminated the planned foundation-pad upgrade — and the speed of installation closed out the full insulation scope 10 days ahead of plan, with only four insulators working 8-hour shifts.

6,000lb
Weight removed
Versus the cal-sil + Pyrocrete® baseline.
10days
Ahead of schedule
Full insulation completed early.
4
Insulators on shift
Small crew, 8-hour shifts, pre-TAR.

Pad-load limit on your next vessel?