Case Study · No. 036 · Cryogel® Z
Cryogel® Z Refining Saudi Arabia

Live cold service line at a refinery on the Red Sea coast, KSA.

A retrofit completed on a running −35 °C line, with no shutdown.

An 8-inch cold service line insulated with polyisocyanurate (PIR) was icing, cracking, and running surface temperatures as high as 1 °C — evidence of thermal conductivity degradation of up to 1800% outside original specification. 30 mm of Cryogel® Z replaced 60 mm of failed PIR while the line stayed in service.

$148
per meter, per year average energy savings after replacing degraded PIR with Cryogel® Z
Degraded PIR insulation with surface icing on the 8-inch cold service line
8-in cold service line · degraded PIR with surface icing, before the retrofit
Product
Cryogel® Z
Industry
Refining
Application
8″ cold service line @ −35 °C
Location
Red Sea coast, KSA
Outcome
Asset integrity with lower environmental impact
01 · The Challenge

Degraded PIR turned a cold line into a hidden energy drain.

Surface icing, condensation dripping, widespread insulation cracking, and external temperature measurements between 1 °C and 27 °C against an expected 32 °C touch temperature — all signs of a system no longer insulating.

  • Thermal conductivity degraded up to 1800%. Field readings taken in April 2025 measured surface temperatures higher than below specification.
  • 240.6 W/m of heat gain at the worst points. Calculated with the ASTM C680 tool against actual temperature data — over 2,100 kWh per year per meter.
  • $166 per meter per year in electricity. Refrigeration load rose in direct proportion to the heat ingress.
  • Condensation and CUI risk. Surface icing and condensation led to cracking and led to corrosion under insulation and pushed up maintenance overhead.

Surface icing and cracked PIR on the live line · measured surface temperatures along the 8-in line, April 2025.

02 · The Solution

Cryogel® Z installed on a live line, with full operational continuity.

30 mm of Cryogel® Z replaced 60 mm of PIR without a shutdown needed — a first-of-its-kind retrofit executed with no production loss, on a pipe still running at operational temperatures.

  • Crews briefed and trained. Cryogel Z® installs quickly and easily, needing minimum training time.
  • PIR and frost removed, then pre-cut blanket applied. Cryogel® Z went on as pre-cut sections followed by vapor barriers and protective jacketing.
  • Flexibility made speed possible. The blanket format allowed fast, precise fitting under live, low-temperature field conditions — at half the installed thickness.

Pre-cut Cryogel® Z applied section by section, then vapor barrier and protective jacketing — all with the line in service.

03 · The Outcome

Heat gain cut by an order of magnitude — and the surface came back to spec.

Expected heat gain on the retrofitted line fell to 25.8 W/m, taking annual energy cost from $166 to $18 per meter — an average saving of $148 per meter per year against the degraded PIR it replaced. Surface temperature at the monitored point moved from 12.8 °C before installation to 32.5 °C after, back in line with the 32 °C touch-temperature specification.

The savings figure is conservative: lower surface temperatures were recorded across multiple sections following installation, so system-wide savings may be greater. Beyond the energy number, Cryogel® Z brings proven resistance to moisture and CUI, and is reusable after turnaround events — reducing reinstallation time and material waste from the maintenance plan while reducing refrigeration power demand and CO₂ emissions.

241 → 26W/m
Heat gain
~90% reduction in heat gain
$166 → $18/m/yr
Energy cost
Electricity cost of refrigeration load per meter of line.
12.8 → 32.5°C
Surface temperature
Before and after installation, against a 32 °C touch-temp target.
60 → 30mm
Installed thickness
Half the profile of the PIR system it replaced.

Before and after surface readings taken with the same infrared thermometer

Got a cold service line you can’t shut down?

Cryogel® Z can be retrofitted on a live line at half the thickness of PIR — Aspen engineers can model the heat gain and payback on your scope or specification.